2,934 New PMP Questions & Answers with explanation

2701.
At the beginning of the project, a project manager realized the technical expertise of the team was limited, a risk to the project. Midway through the project, the project manager decided that this was no longer a risk and considered it outdated. As part of which process would he do the risk reassessment?
Select one
2702.
You are meeting with your stakeholders to gather requirements for your project. You are well aware that requirements to be gathered include both product and project requirements. All the following tools can be used to gather, define, and analyze project requirements from stakeholders except:
Select one
2703.
A project manager is looking at a make-or-buy analysis as part of the Procurement Management process. What type of costs should the project manager consider for this analysis?
Select one
2704.
Which of the following is not an input to the Conduct Procurements process?
Select one
2705.
During the execution of a project, a large number of defects were discovered. The project manager ensured that the issues, defect resolution, and action item results were logged into a defects database. What would the defect database be considered a part of?
Select one
2706.
The WBS structure can be created in a number of forms except which of the following?
Select one
2707.
A project manager is currently ensuring that the stakeholders clearly understand the project goals, objectives, benefits, and risks. This relates to which of the following processes?
Select one
2708.
Joe has been managing a project for Exton Oil Corp. This project involves redesigning filling stations across the state. The redesign involves new gas pumps, security cameras, convenience stores, and use of environmentally friendly materials in the construction. While the redesigning work proceeds, Joe’s design engineer suggests a secondary alarm system for gas pumps to alert the attendant in case of a spill. Although this suggestion is not in the project requirements, Joe is impressed with the engineer’s recommendation. What should be the next step for Joe with regard to the engineer’s suggestion?
Select one
2709.
Which of the following structures helps track project costs and can align with the organization’s accounting system?
Select one
2710.
A first-time project manager is advised by an experienced project manager to plan for cost of quality. The first-time project manager is not sure which costs are included in the cost of quality. What would your advice be?
Select one