2,934 New PMP Questions & Answers with explanation
2711.
As part of earned value management (EVM), a project manager is calculating the to-complete performance index (TCPI) based on EAC. The data he has is as follows: The budget at completion for the project is $100,000. The earned value for the project is $25,000. The actual costs to date are $40,000, and the estimate at completion is $115,000. What is the TCPI that he will get?
Select one
2712.
How can changes be made to a project management plan once the project manager baselines it?
Select one
2713.
The morale of the team members of a project is very low. The team members feel they were not given opportunities to participate in the organizational team development activities due to over-allocation to project tasks, and so, they missed opportunities to develop. Which of the following is the most likely cause of this situation?
Select one
2714.
Given multiple alternatives, the group decision method that allows the largest block in a group to decide (even if more than 50 percent of the members of the group do not support the decision) is:
Select one
2715.
In a multi-phase project, the procurement team decided to close the procurements applicable to a particular phase of the project. What happens to unresolved claims?
Select one
2716.
During the Control Scope process, analysis of the scope performance resulted in a change request to the scope baseline. This change request will be processed for review and disposition in the:
Select one
2717.
The quality cost of a project rose significantly during the course of the project. A post-mortem analysis of the increased cost revealed that this was due to poorly defined acceptance criteria. During which phase should the acceptance criteria have been properly captured?
Select one
2718.
The project management team expects that during the course of the project there could be delays in component delivery due to strikes, changes to the permitting processes, or extensions of specific engineering durations. What analysis could be helpful in preparing contingency and response plans to mitigate these issues?
Select one
2719.
In the earned value management technique, the cost performance baseline is:
Select one
2720.
A seller entered into a contract with a buyer. At the end of the project, the seller was reimbursed for the cost of the project but received a low fee based on certain subjective criteria that were specified in the contract. What type of contract is this likely to be?
Select one