89 New PMP Procurement Questions & Answers with explanation
31.
Which of the following techniques can help clarify the structure, requirements, and other terms of the purchases so that mutual agreement between a buyer and a seller can be reached prior to signing the contract?
Select one
32.
A number of deliverables were submitted to the buyer as part of a project. Where would the project manager find documentation on the requirements for formal deliverable acceptance and on how nonconforming deliverables can be addressed?
Select one
33.
Which of the following is incorrect regarding a bidders conference?
Select one
34.
The source selection criteria for all procurements in a project is developed during which of the following processes?
Select one
35.
During the Conduct Procurements process, the procuring organization found that there were significant differences in pricing by different sellers. What is the best course of action in such a scenario?
Select one
36.
Which of these is not an input to the Control Procurements process?
Select one
37.
Which of the following is not a tool or technique of the Control Procurements process?
Select one
38.
You have received a proposal for an RFP that was sent to vendors. One of the vendors has proposed doing the project for $12,500. The cost for the project is $10,000, and their profit will be $2,500. Which type of contract is most suitable if the type of work is predictable and the requirements are well-defined and not likely to change?
Select one
39.
Your company requires that before you purchase any routers or switches for the data center you are building, you need to solicit quotes from three separate suppliers prior to submitting the purchase request to the finance department. This policy belongs to:
Select one
40.
Which of the following is accurate regarding agreements in Project Procurement Management?
Select one