89 New PMP Procurement Questions & Answers with explanation

51.
What type of method uses a weighting ranking system for quantifying qualitative data to minimize the effect of personal bias during the process of selecting a seller?
Select one
52.
A project is contracted on a Cost-Plus-Fixed-Fee (CPFF) basis. The targeted cost is US$200,000 with a fee of US$30,000. If the project comes in at US$170,000, what would be the total cost of the contract?
Select one
53.
You are a project manager for your company. Part of the project requires producing 10,000 widgets, which your company will outsource. The company has agreed to pay all related costs and 5 percent of the estimated project costs. What type of contract has been negotiated?
Select one
54.
As part of the procurement process, the procuring organization elected to have an estimate of costs prepared by an outside professional estimator. The estimator came up with an estimate of $500,000. However, the cost estimates prepared by prospective sellers were in the range of $200,000. How can this be best interpreted?
Select one
55.
In a multi-phase project, the procurement team decided to close the procurements applicable to a particular phase of the project. What happens to unresolved claims?
Select one
56.
A seller entered into a contract with a buyer. At the end of the project, the seller was reimbursed for the cost of the project but received a low fee based on certain subjective criteria that were specified in the contract. What type of contract is this likely to be?
Select one
57.
A project manager is looking at a make-or-buy analysis as part of the Procurement Management process. What type of costs should the project manager consider for this analysis?
Select one
58.
Which of the following is not an input to the Conduct Procurements process?
Select one
59.
Which of the following statements is correct?
Select one
60.
Many organizations favor fixed-price contracts because the buyer's risk is minimized by such contracts. However, to minimize the seller's risk, which of the following is crucial for a fixed price contract?
Select one