89 New PMP Procurement Questions & Answers with explanation

81.
The performance reports produced during the Control Procurements process are then provided to which project management process for further processing?
Select one
82.
Which of the following techniques can help a project manager review a supplier’s internal work processes to ensure compliance to standards during the production of the deliverables? (Assume that all of the given choices are available to the project manager.)
Select one
83.
You have recently joined an organization as the procurements manager. You have just received an invoice from a contractor. Some of the items from the invoice are as follows: EV of work completed to date: $50,000. AC of work completed to date: $40,000. Total costs reimbursed by the buyer to date: $35,000. If the contract between the buyer and the contractor is a CPIF contract, what is the total value payable to this contractor? (Assume that the contract allows for a 10 percent fee over net payable whenever CPI > 1).
Select one
84.
While rating a proposal, one of the requirements was: "The proposed project manager needs to be a certified Project Management Professional, PMP®" This is an example of:
Select one
85.
A project is contracted on a Cost-Plus-Incentive-Fee (CPIF) basis. The contract states that if the final costs are less than expected costs, the sharing formula for cost savings is 80:20. The targeted cost is US$500,000 with a 10 percent fee. If the project comes in at US$450,000, what would be the total cost of the contract?
Select one
86.
A seller began a project that was contracted on a time-and-materials (T&M) basis. Based on the agreed-upon rates and effort, the initial contract amount was $100,000 over a one-year period. However, when the project was completed, the total contract value turned out to be $350,000 over a two-year period. What mechanism could the buyer have used to prevent this unlimited cost growth and schedule change?
Select one
87.
Which of the following roles in a project is most likely to be involved in negotiations on procurements during the Conduct Procurements phase?
Select one
88.
Your drug manufacturing project requires the synthesis of many pharmaceutical chemicals to produce an active ingredient for a drug. You are managing a contractor to supply all these chemicals. Recent quality testing of the drugs raised concerns over the quality of the chemicals supplied by the contractor. Which of the following must be your first action to ensure that the contractor is meeting all contractual obligations?
Select one
89.
Organizations evaluate whether to buy products or make the items themselves. Which of the following is not a factor that influences makeor-buy decisions:
Select one