2,934 New PMP Id 1028 project management is concerned with managing which type of project Questions & Answers with explanation
191.
A large project involving functional groups in four countries is nearing completion. The project manager is preparing closeout documents. Who should sign off on the acceptance of project deliverables?
Select one
192.
A project manager prepares the charter for a project that aims to automate 20 percent of product testing. The project sponsor advises the project manager to assign senior test engineers to identify the tests that can be automated. However, the test department manager is uncooperative because they believe that the project will cause downsizing in their department. What should the project manager do first?
Select one
193.
A project team has fallen behind schedule on some tasks. The project manager tries to fix the issue by reprioritizing a few subsequent tasks. This does not resolve the scheduling problem, and the project manager must now escalate the issue to the project's stakeholders. To what plan should the project manager refer to escalate this?
Select one
194.
A sponsor is very upset because they did not know about a project change to reduce the budget. The project manager and project team do not understand the sponsor's frustration, because the change was required and beneficial to the project. What should the project manager have done first?
Select one
195.
A final deliverable will not be completed on time, which is delaying project closure. What should the project manager do next?
Select one
196.
A project manager is concerned that team members spend too much time assisting operations and maintenance staff with a recently commissioned project component. To what documents should the project manager refer to validate that the component was signed off and ownership transferred?
Select one
197.
A highway construction project is on schedule and within budget. The project manager has just learned that an unforeseen mineral reserve has been discovered on the site. This will require that the highway is diverted, which will displace neighborhoods. What project management tools or skills will the project manager need to handle this?
Select one
198.
A team lead is concerned that two project teams are working on parts of the project that are highly dependent on each other. The team lead believes that this might create conflicts when the two teams' outputs are combined. What should the project manager instruct the team lead to do?
Select one
199.
A new project manager joins an ongoing project following the resignation of the former project manager. What should the new project manager do to start guiding the team toward project success?
Select one
200.
One week prior to a kick-off meeting, a project manager meets with a key project resource to understand the complexity of the project deliverables. The resource is apprehensive about the deliverables and expresses concerns. What should the project manager do to ensure that the deliverables are realistic?
Select one