2,934 New PMP Id 1028 project management is concerned with managing which type of project Questions & Answers with explanation

251.
A project team is performing above service levels, and there have not yet been any issues. However, there are concerns about whether or not this level of performance is sustainable. What should the project manager update?
Select one
252.
Due to scope changes during project execution, the project manager identifies that a provider must make changes to a product module already in use. What should the project manager do first?
Select one
253.
Midway through a project, the project sponsor replaces a key resource with a new hire. What should the project manager do first?
Select one
254.
There are three main tasks in a new product development project. Task A must be delivered two weeks before task C starts, and task C will start once task B is finished. What is the relationship between tasks A and B?
Select one
255.
During a project's execution phase, a regulatory law is approved that mandates immediate compliance. This law will impact the project's scope, schedule, and cost. What should the project manager do first?
Select one
256.
A project that should have been 80 percent complete by now is only 75 percent complete. The total project budget is US$100,000 and the actual cost of work performed (ACWP) is US $72,000. What can be determined from this information?
Select one
257.
High failure rates are found in the production line during product manufacture. The project deadline is tight, and the cost of pending production is high. The engineers have determined the root causes of the problem and the project team has identified the best solution. However, this solution will require an increase in the budget. What should the project manager do?
Select one
258.
A project sponsor directs a project manager to immediately begin a critical project with a very tight timeline. What should the project manager do first?
Select one
259.
During a project progress meeting, a stakeholder informs the team that a previously identified technical issue has been resolved. However, the stakeholder warns that the same issue is likely to happen on other, similar projects. What should the project manager do first?
Select one
260.
A project has become so large that the single sponsor is replaced by a steering committee. What should the project manager do to accommodate this new development?
Select one