2,934 New PMP Id 1028 project management is concerned with managing which type of project Questions & Answers with explanation
261.
A team member informs the project manager that there is a variance between actual and planned system speed. The project manager is surprised, because this performance measurement was not identified during the planning phase of the project. The project manager then evaluates whether the variance requires a response. During the evaluation, in which phase is the project manager?
Select one
262.
A multinational company initiates a project to develop a human resource information system (HRIS) to centrally manage human resource and payroll processes. So far, the project manager has considered the regulatory framework of the project and reviewed historical data on the company's human resource practices. The project manager is worried about project risks. What should the project manager do?
Select one
263.
A project resource completed all assigned project tasks. The resource's manager requests an immediate transfer of the resource to another project. What should the project manager do next?
Select one
264.
After project closure but during the warranty period, the project manager wants to determine whether the customer is satisfied with the project's outcome. How can the project manager measure this?
Select one
265.
A risk is identified during a project that was not anticipated during planning. How should the project manager respond to the risk?
Select one
266.
While developing the project schedule, the project manager realizes that the high-level timeline is unrealistic due to longer-than-expected procurement lead times for certain key project components. What project document should the project manager update?
Select one
267.
A project issue is identified after implementation in the production environment. What tool or technique should the project manager use to identify the reason for the issue?
Select one
268.
For a long-term infrastructure project, the project manager must acquire suppliers with the lowest possible risk due to the global business climate. What type of contract should the project manager use?
Select one
269.
A project manager is ready to close a project. What should the project manager do next?
Select one
270.
During project implementation, the marketing department informs the project manager that the product's market requirements have changed. These changes were not anticipated, may significantly influence potential sales numbers, and could impact project scope. What should the project manager do?
Select one