2,934 New PMP Id 1028 project management is concerned with managing which type of project Questions & Answers with explanation

301.
A project team discovers that there are many detailed capabilities that differ from the scope outlined in the project charter. What should the project manager use to manage this?
Select one
302.
A project manager is uncertain about the duration of a new product and consults several groups of subject matter experts (SMEs). The first group advises that development can be finished in 30 days. The second group identifies some risks that could make the duration up to 45 days. The third group proposes a new development method that can shorten the time to 21 days. What is the estimated development duration for the new product?
Select one
303.
A team member is eager to add new features being considered by the customer to the project deliverable. Before beginning work on these new features, whose approval is required?
Select one
304.
A project manager joins a project during its planning phase. What should the project manager do to become familiar with the project's status?
Select one
305.
A project team failed to consider a critical technical aspect on a project requirement. A quality audit demonstrates that this issue would prevent the end product from meeting its quality requirements. What should the project manager do first?
Select one
306.
A strategic project is about to begin user acceptance testing. Weekly progress meetings have been set up to prepare for testing with the business end users who have repeatedly raised questions and concerns. It is evident that there are critical business requirements that failed to be included in the business requirements analysis. What should the project manager do?
Select one
307.
A new, recently released technology can speed up the development tasks on an ongoing project by 30 percent. The team is eager to use this new technology, but identifies the risk that issues may arise due to a lack of knowledge and support. How can the project manager and the team decide if the project benefits by using this technology?
Select one
308.
A project manager has obtained final acceptance of the deliverables, completed the assessment, released project resources, and closed out all procurement-related activities. What should the project manager do next?
Select one
309.
Due to time constraints, a project manager omits the review of previous lessons learned. What is a potential impact of this decision?
Select one
310.
A project has ended; however the project manager and project team members are still called to solve technical issues, make some small changes, and evaluate new requirements. What should the project manager do to guarantee the product or service developed by the project now has operational support?
Select one