2,934 New PMP Id 1028 project management is concerned with managing which type of project Questions & Answers with explanation
Match the following categories associated with analyzing stakeholders in the Salience
model with their classification.
Category | Classification | |
Legitimacy + urgency
|
Dangerous
|
|
Power
|
Dependent
|
|
Power + urgency
|
Dominant
|
|
Urgency
|
Dormant
|
|
Legitimacy
|
Discretionary
|
|
Power + legitimacy
|
Demanding
|
A project sponsor is risk averse and is therefore concerned about negative impacts on the project. To help with this concern, the project team identifies four project risks and then evaluates both the probability of occurrence and the impact of the risk if it occurs. The team uses a 1-5 scale, 1 being the lowest and 5 being the highest.
Based on the table, in what order should the project manager rank these risks for risk management purposes?
Your sponsor has committed to building a high-speed rail from one major inland city, Azules, to the coast. You have two possible routes, either Brazos or Corazon. Given each route's costs, odds, and rewards of high demand and low demand in this decision tree, how would you quantify the expected monetary value of the route to Brazos?
The following Gantt chart displays the schedule for a software upgrade project. The system analysis was completed on August 12th, but the system design and development activities are still in process as of October 3rd. Once the product is developed, the project team will need to test and deploy it, which must be completed by October 17th. What is the cost variance as of October 3rd?
A project manager is currently managing a manufacturing process improvement project which will be completed in five phases. The project manager has prepared the following chart to review the status of the project. Based on the information provided, what is the earned value of the project?
Following is an illustration of a project network activity node that includes some information about activity D. Given the information provided, what is the total float of activity D?
The following table is an activity list that includes the duration and predecessor for a series of project activities. What is the duration of the critical path?