New PMP Question & Answers with explanation

A project manager is currently managing a manufacturing process improvement project which will be completed in five phases. The project manager has prepared the following chart to review the status of the project. Based on the information provided, what is the earned value of the project?


Select one
You are in the process of developing an approximation of the monetary resources needed to complete project work for a large-scale multinational project which will take at least seven years to complete. Your previous projects have all been domestic with short timeframes. As part of the process you are currently performing, what might you need to do differently compared with your past projects?
Select one
A project manager is developing a cost management plan and needs to determine the best source of funding for a project that is dictated by a legal requirement. The cost of capital is estimated at 9.7% for non-dividend paying equity, 6.7% for debt, and 5.1% for self-funding. The NPV of the project is $500,000 with an opportunity cost of $750,000. What is the project manager's best course of action?
Select one
The project has reached a stage where work is being done in seven countries. Project team members need to know in which currency they are to report their cost data. Which of the following should they reference?
Select one
A project team member runs an earned value analysis (EVA) report. There is an unexpected spike in actual costs over the last three weeks. The team member shows the report to the project manager and based on her analysis presents four possible reasons for the spike. Which reason is most probable?
Select one