New PMP Question & Answers with explanation
During project execution, a functional manager identifies a new internal risk about the outsourcing team. The functional manager asks the project manager for a fast solution that will not negatively impact the project. What should the project manager do?
Select one
An experienced project manager resigns, and a new project manager joins the team. During the initial assessment of project documentation, the new project manager discovers that the risk register has not been updated for the past month. What should the project manager do first?
Select one
A project manager learns that the customer's resources have not completed the required training. Since customer resource training is a required project deliverable, this poses a risk to the timely completion of the project. What should the project manager do?
Select one
A project manager is aware of two critical, high-impact risks that must be addressed immediately. However, the necessary resources to address the risks are already committed to another project with critical deliverables. What should the project manager do?
Select one
A project manager is preparing the monthly project status report. Some new risks have been identified that could impact important key milestones. What should the project manager reference before presenting this new risk information?
Select one