47 New PMP Questions & Answers with explanation

31.
Each critical project communication requirement must be carefully analyzed. One good way is to use a communication model to design effective communications. What is the sequence of steps in a basic communication model?
Select one
32.
Lucy is managing a high-tech software development project. She has luckily acquired the organization’s best performing employees. However, the project team is not communicating effectively, causing delays. The project communications plan is in place, but it seems as if the employees are not following it. The communications plan lays out the communications requirements but does not explicitly assign responsibilities. What should Lucy do first? (Assume that all the following actions need to be taken at some stage.)
Select one
33.
Complex projects usually demand preparation and distribution of periodic project performance reports. The contents of performance reports are usually determined early and documented in the project communications management plan. Which of the following is least likely to be a section on a work performance report?
Select one
34.
David’s project is currently in difficult times, and the project stakeholders are not happy with the project updates they receive. In a meeting with the project sponsor, David said the stakeholders’ attitude is irrational since he personally ensures that all project communications are accurate and timely. Mary, the project sponsor, advises David that he needs to go the extra mile in managing the stakeholders rather than just managing the project communications. What does Mary mean?
Select one
35.
The methods used to transfer information among project stakeholders may vary significantly. A project team may apply different techniques and communication technologies to ensure effective and efficient communications. Which of the following must not be a factor to consider while choosing a communication technology?
Select one
36.
To ensure effective communications throughout a project lifecycle, a project manager should develop a communications plan early in the project. When developing a communications plan, a project manager must consider a number of factors. Which of the following is the least important consideration among the list while developing a communications plan?
Select one
37.
Tim is the project manager of a project that has a timeline of 18 months. Tim plans to send daily status reports to all stakeholders. After receiving two such reports, Sue, the project sponsor, informs Tim she would like to have reports every two weeks only. Tim did an analysis of communications requirements and considered various attributes for the communications management plan. What aspect has he missed, which resulted in a daily status report being sent instead of two-week status reports?
Select one
38.
Gene is the project manager of a large highway expansion project. He has a number of stakeholders with competing priorities and agendas, and he often has to resolve conflicts among stakeholders. Which knowledge area manages communications with the project stakeholders?
Select one
39.
Which of the following is NOT considered a method in the Manage Communications process?
Select one
40.
No matter how good you are in communicating, information distribution to stakeholders as planned is a challenging task. Many tools and techniques are used during the Manage Communications process except:
Select one