47 New PMP Questions & Answers with explanation

21.
All of the following are true regarding the organizational process assets updates output of the Manage Communications process except for which one?
Select one
22.
Wendy is a project manager for an IT data center installation in a country that recently established independence. The country is in a strategic location for fiber optic communications, but the political climate is highly unstable. In order to keep the data center in the country but avoid unnecessary influence from the political dynamics, Wendy has negotiated with the U.S. Department of State to establish the data center in the basement of the U.S. Consulate in the capital city. This is an example of:
Select one
23.
In a steering committee meeting for a project to build a new state-of-the-art communications device, the committee chair reprimands the project manager for not using the company’s file sharing system as required by the organization. The project manager explains that the project team chose a newer tool for the project, as it was much better. What most likely caused this situation?
Select one
24.
You are developing the communications management plan for a construction project. You want to determine the information needs of the project stakeholders, specifically focusing on the type and the format of information that will be required to communicate with the stakeholders. What is your best course of action?
Select one
25.
A new project is starting, and the team members come from all over the world. The project manager has concerns about communications. What should the project manager do first?
Select one
26.

You have just taken over a project to overhaul the company's telecommunications network. During your first week, you determine that the engineers spend at least 80% of their time responding to unexpected requests for information from different project stakeholders. Because of these interruptions, your engineers cannot focus on their assigned project activities, which is resulting in frequent network outages. What should you do first?

Select one
27.
A project manager has just taken over the project from another project manager during the executing process group. The previous project manager created a project budget. Determined communications requirements and went on to complete work packages. What should the new project manager do next?
Select one
28.
A project manager has just taken over the project from another project manager during project executing. The previous project manager created a project budget, determined communications requirements, and went on to the complete work packages task. What should the new project manager do next?
Select one
29.
Stakeholder notifications must be archived for future reference. Whenever the Manage Communications process produces a stakeholder notification, the notification must be:
Select one
30.
Robert has recently joined an automobile manufacturer. He now has a project that was already in the execution phase. Recently, one of the key stakeholders has raised serious concerns over the project’s scope. Robert now wants to review the previous project communications to understand how the current project scope was agreed to by all key stakeholders in the past. Where can he find this information?
Select one