47 New PMP Questions & Answers with explanation

41.
James is managing a shopping mall construction project. During the project execution, he learns the project communications management plan is not effective and requires a major update. Which of the following processes will issue a change request for the required update?
Select one
42.
Along with the project communications management plan, work performance reports are vital inputs to the Manage Communications process. Where do these work performance reports come from?
Select one
43.
Sandra is managing a complex ERP design and implementation project. The project team has recently been hired. It is an enterprise-wide project affecting many stakeholders. It is very important for each team member to properly understand and follow the project communication requirements in order to keep the stakeholders engaged and informed. Which of the following tools and techniques can Sandra use to ensure that team members properly understand the project’s communications requirements?
Select one
44.
Mary is currently drafting a stakeholder engagement plan for her new website development project. Her organization has strict communication guidelines. Mary wants to ensure that her stakeholder engagement strategy aligns with the organizational communications guidelines. Where can she find these guidelines?
Select one
45.
Nancy has recently become the project manager for a project already in execution. Nancy has learned the previous project manager did a good job so far and religiously followed the PMBOK guiding principles. However, some of the project communications don’t make sense to her. Which of the project artifacts should Nancy refer to in order to determine reasons for distribution of some reports?
Select one
46.
Which of the following are the tools and techniques used in both the Plan Communications Management and Manage Communications processes?
Select one
47.
Communications management plans should include all of the following except:
Select one