196 New PMP Cost Questions & Answers with explanation

81.
Which of the following defines things the project manager needs to do regarding cost
Select one
82.
While reviewing project performance, the project manager determines that the schedule variance is -500. What is the best thing to do
Select one
83.
One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and:
Select one
84.
Which of the following information about the project would never be available during project planning
Select one
85.
Which of the following represents the estimated value of the work actually accomplished?
Select one
86.
A cost performance indes (CPI) of 0.89 means
Select one
87.
You take over a project that is us $100,000 over budget. You know the team has completed us $500,000 worth of work. Your sponsor has been calling all day leaving messages while you were in meetings asking for a quick update on the project status. What will you tell him when you return his call?
Select one
88.
You are in the middle of project executing and find you are running out of money due to unanticipated changes. What is the best thing to do
Select one
89.
You provide a project cost estimate for the project to the project sponsor. He is unhappy with the estimate, because he thinks the price should be lower. He asks you to cut 15 percent off the project estimate. What should you do?
Select one
90.
This has been determined that six additional computers are needed to complete the project. The computers are an example of
Select one