196 New PMP Cost Questions & Answers with explanation

51.
You are reviewing the expense report form one of your team members when you notice a payment he made in another country. You think the payment is bribe. What is your first course of action
Select one
52.
Which of the following is an example of a parametric estimate?
Select one
53.
You are a project manager for a small construction project. Your project was budgeted for u.s. $72,000 over a six week period. As of today, you've spent u.s. $22,000 of your budget to complete work that you originality expected would cost u.s. $24,000. According to your schedule, you should have spent u.s. $30,000 by this point. Based on these circumstances, your project could be best described as:
Select one
54.
A definitive estimate is in a range from
Select one
55.
Which of the following are all items included in the cost management plan?
Select one
56.
Your company is undergoing a change in ownership and the new owners are looking at the total cost of a new product. Which of the following would best provide that information
Select one
57.
You are tracking your project using earned value management (evm) and find you are behind schedule but under budget. Your variances show schedule variance (SV) = -us $50 million, cost variance (CV) = $100 million, and your actual costs are us $500 million. What are the cpi, pv and spi?
Select one
58.
A project manager has just been notified of a cost increase by a seller. He looks at the contract and determines that the seller has the right to pass along this cost increase. The project manager should fist determine if
Select one
59.
What does estimate at completion (EAC) mean
Select one
60.
The project sponsors have asked you to assess the feasibility of meeting the objectives and cost constraints. .why should you use analogous estimating
Select one