196 New PMP Cost Questions & Answers with explanation

91.
How close to actual costs should a definitive budget estimate be
Select one
92.
Which of the following is a key way to improve activity cost estimates
Select one
93.
The plan cost management process addresses all the following except
Select one
94.
A cost management plan contains a description of:
Select one
95.
A project manager is analyzing the project to find ways to decrease costs. It would be best the project manager looks at
Select one
96.
The six-month project has 300 work packages and a us $600,000 budget. Three months into the project, 150 work packages are complete and us $300,000 has been spent. Which of the following is correct?
Select one
97.
Identified risks are:
Select one
98.
A project team budgeted us $3,000 for the work performed and has spent us $4,000 to date. If they budgeted us $5,000 for the work sccheduled, what is the cost variance (CV)?
Select one
99.
What is the difference between expected monetary value and net present value
Select one
100.
The project manager has been asked to explain what occurred and what will be done to keep to the budget. Which calculation is the project manager likely to use as a measurement tool to analyze this inforrmation?
Select one