196 New PMP Cost Questions & Answers with explanation

71.
The difference between the cost baseline and the cost budget can be best described as:
Select one
72.
Estimate at completion (EAC) is a periodic evaluation of:
Select one
73.
Monitoring cost expended to date in order to detect variances from the plan occurs during:
Select one
74.
You have estimated the project cost to be us $850k within -25/+75 percent of actual. This is a
Select one
75.
The cost contingency reserve should be:
Select one
76.
Your project has a AC = $800million, PV = $890millions, and a CPI = 1.1. How is the project going?
Select one
77.
Cost performance measurement is best done through which of the following?
Select one
78.
Your cost forecast shows that you will have a cost overrun at the end of the project. Which of the following should you do?
Select one
79.
What would be the best explanation for the following: both the cost variance and schedule variance are negative, but the cost variance is lower than the schedule variance
Select one
80.
Your organization is hoping to meet its strategic objective to grow the business by expanding to foreign markets. Since working with international sellers is new to you as a project manager you are researching potential issues others have encountered on international projects. You have learned of situations where issues have arisen due to illegal payments. Which e following payments on an international project is unacceptable?
Select one