361.
A company is venturing into a new business but has no previous experience in that market. What tool or technique should the project manager use to collect requirements?
Select one
362.
A customer identifies performance issues on a newly implemented product. What category of cost of quality (COD) should the project manager have used to estimate this cost?
Select one
363.
While reviewing the quality of deliverables with the team, the project manager determines that several quality issues could have been avoided by using a simple checklist. The checklist is then implemented for future deliverables. What did the project manager do in this situation?
Select one
364.
A project manager joins a new multi-million-dollar project that requires deliverables from various departments to successfully implement. What should the project manager do first to successfully implement the project?
Select one
365.
A project manager notices schedule performance issues due to the expertise levels of project resources. Some experienced resources check unnecessary details, and some junior-level resources take a long time to complete tasks. What should the project manager do to enhance team performance?
Select one
366.
A project manger in a global organization is responsible for a project involving six different companies. Midway through the project, one stakeholder's involvement is lessened due to illness. What should the project manager update?
Select one
367.
A project is ready to close, but a vendor claims they have not received payment. The project manager sees that payment was approved, but is unable to find supporting documents from the finance department. The project manager wants to close the project due to a new assignment. What should the project manager do?
Select one
368.
A project manager submits a project review report showing that the project has completed 50 percent of its activities, has a schedule performance index (SPI) of 1, and a cost performance index (CPI) of <1. What should the project manager do next to successfully complete the project?
Select one
369.
A project team has invited many of the project stakeholders to help them inspect quality on the project. Which of the following would not be an output of this activity?
Select one
370.
The code development phase of a software project is nearly complete when the first code review is conducted. During the review, it is discovered that the application is missing functionality required to complete a key business process. However, the product scope never specified this functionality. What should the project manager do?