2,934 New PMP Questions & Answers with explanation
331.
A senior project manager is guiding a new project manager in finalizing project activities. What should the senior project manager list as the key benefits of documenting final project activities?
Select one
332.
A supplier has been awarded a firm fixed price (FFP) contract to provide various materials for a construction project. The contractor has received all pertinent documents relating to material standards and specifications. By contract, the supplier must deliver all materials to the construction site on a specific date. When the materials arrive at the site on time, what should the project manager do?
Select one
333.
During project implementation, a functional manager asks to include additional functionality that will benefit the customer. What should the project manager do?
Select one
334.
A food company receives customer complaints that a product is underweight. What tool or technique can the project manager use to determine if something needs to be changed in the production line?
Select one
335.
A project has been successfully delivered and the project manager is executing formal closure. What should the project manager do first?
Select one
336.
A project is being executed when a few changes are brought to the attention of the team. The changes are needed but everyone has different opinions on what they think is right. What should the project manager do?
Select one
337.
A project manager is working on a project taking place in many cities throughout the country. During the final stages of execution, a team leader informs the project manager that work has stopped in one city due to safety issues. Authorities will not allow further project work for three months pending an investigation. What should the project manager do?
Select one
338.
During project execution, a stakeholder requests a change to ensure that the final product will satisfy their requirements. What should the project manager do next?
Select one
339.
Several months after the implementation of an approved change to manage a risk, a project manager learns that the change failed to achieve the expected result. This led to adverse consequences. What should the project manager have done to avoid this?
Select one
340.
A project manager joins a project that has just started. The sponsor and project team assure the new project manager that the project has an adequate budget and realistic schedule. The project manager is concerned about unplanned events that could threaten the project's success. What should the project manager do?
Select one