2,934 New PMP Questions & Answers with explanation

801.
During your project meeting, a problem was discussed, and a resolution to the problem was reached. During the meeting, the participants started wondering why they thought the problem was such a big issue. Sometime after the meeting, you received an email from one of the meeting participants saying they've changed their mind about the solution reached in the meeting and need to resurface the problem. The solution reached during the initial project meeting is a result of which of the following conflict resolution techniques?
Select one
802.
Name the difference between the agile iterative approach and the agile incremental approach as discussed in the Agile Practice Guide (PMI®, 2017).
Select one
803.
Which of the following statements regarding configuration management is not true?
Select one
804.
Project managers spend what percentage of their time communicating?
Select one
805.
These types of dependencies can create arbitrary total float values and limit your scheduling options.
Select one
806.
The project sponsor has approached you with a dilemma. At the annual stockholders’ meeting, the CEO announced that the project you're managing will be completed by the end of this year. The problem is that this is six months prior to the scheduled completion date. It's too late to go back and correct her mistake, and now stockholders expect implementation by the announced date. You must speed up the delivery date of this project. Your primary constraint before this occurred was the budget. Choose the best action from the options listed to speed up the project.
Select one
807.

A small sample of your project’s critical path is shown in the following table. Assuming each activity must finish before the next activity can begin, which of the following options is not correct?

Activity
Duration
Early Start
Early Finish
1225/15/22
255/235/28
375/96/4
41

Select one
808.

A small sample of your project’s PERT calculations is shown here. Activity 2 is particularly important to the project, and your stakeholders are asking for a confidence level for this activity. You tell them there is a 95.44 percent chance of completing activity 2 within how many days?

Activity
Optimistic
Pessimistic
Likely Expected Value
1101412
2203023
3333
Select one
809.

A small sample of your project’s PERT calculations is shown here. What is the total duration of the project?

Activity
Optimistic
Pessimistic
Likely Expected Value
1101412
2203023
3333


Select one
810.
Your project has a total of 35 stakeholders. How many lines of communication exist?
Select one