767 New PMP Process Questions & Answers with explanation

471.
You are managing a software development project with a team that is colocated. The project is managed through a set of iterations that begin with the creation of story cards. The focus of each iteration is to deliver business value, with programmers working together in pairs and as a group. Which of the following are true regarding this question?
Select two
472.
As a result of a face-to-face meeting you recently had, you have resolved an issue and have come away with an update to the issue log, change requests, project management plan updates, and project documents updates, and you have submitted a change request. You know all of the following are true regarding this except which one?
Select one
473.
Your project team is struggling to complete the latest set of features, which requires advanced knowledge of facial recognition technology. After considering various options, you decide to create a war room. What are you hoping to accomplish?
Select one
474.
A project manager rallies the team together for one final meeting, which will wrap up with a celebration for the successful achievement of the project’s final feature. During the meeting, the project manager captures feedback from the team about what went well and what could have been improved throughout the project’s life. The project manager also discusses the achievement of planned benefits. In what project artifact will the project manager capture this information?
Select one
475.
Which of the following best describes the purpose of corrective action taken during the Executing process activities of the project?
Select one
476.
Which of the following are elements captured within the team charter?
Select two
477.
During a meeting with the team, you collaborate to prepare stories for the upcoming iteration, with the intention of providing enough information about the stories for the team to understand what the stories are and determine sizing. In what activity are you engaged?
Select one
478.
What is the most commonly used method of performance measurement?
Select one
479.
You are a project manager for SubZero Delights, a company that offers extraordinary experiences to travelers. Your latest project involves the development of a smartphone app that automatically picks up a customer’s GPS coordinates to provide tailored resources and recommendations. You chose a hybrid approach with a goal of delivering results faster and maximizing the speed at which the team can work. Which of the following technical practices can the team incorporate to accomplish this goal?
Select one
480.
Which of the following best describes the purpose of the change log?
Select one