767 New PMP Process Questions & Answers with explanation

491.
The president of the company has asked you to lead a large new project that links to the company’s number-one strategic priority. As a result, you will need to transition one of your other projects to another project manager. During a transitionary meeting, your colleague asks to see the team’s social contract so that they can become familiar with established ground rules. What document are they referring to?
Select one
492.
Which of the following statements about project governance frameworks are true?
Select three
493.
A business analyst has just facilitated a requirements-gathering session. The following week, the project manager begins the process of capturing and documenting the project’s deliverables and creating a WBS. The business analyst and project manager are carrying out processes that belong to which of the following Knowledge Areas?
Select one
494.
Given the following information, are project costs ahead or behind what was planned for this period? EV = 95, PV = 85, AC = 100.
Select one
495.
A project manager is facilitating a meeting to further define user stories for the upcoming iteration. Two team members involved, Bob and Jenny, are very vocal during the start of the meeting, with Jenny passionately noting that the second user story should be punted to the next iteration. She moves on to the next user story, ignoring Bob’s opposing views on the topic. Bob accepts the decision hesitantly and remains quiet for the remainder of the meeting, accepting other decisions made by Jenny and the rest of the team. At the end of the meeting, the project manager notes to Bob that she will prioritize user story #2 at the top of the backlog, to be pulled into the iteration should capacity allow. Which of the following conflict-resolution techniques did Jenny use in this scenario?
Select one
496.
Ronaldo has just joined the company as a project manager and is taking over an active project that is in the process of developing the schedule. The previous project manager did a good job of maintaining project management documents up-to-date. Which project management document can Ronaldo reference that will outline the methodology and tools the team is using to perform schedule network analysis?
Select one
497.
Kaylee is a risk manager working in collaboration with Alyssa, a project manager, and both work for a top healthcare company. They are currently in the process of performing risk analysis. Of the 20 risks identified, 5 are deemed to be low priority. Where will these risks be documented?
Select one
498.
Manfrit and Frank are two project managers who have supported one another throughout their careers. During a casual lunch, Frank asks Manfrit for advice, noting that he has been struggling to get his team to embrace eXtreme Programming practices. He notes that, after undergoing a few training sessions, the team doesn’t understand the terminology and finds it confusing. What advice should Manfrit provide in this situation?
Select one
499.
You are a project manager for SubZero Delights, a company that offers extraordinary experiences to travelers. Your latest project involves the development of a smartphone app that automatically picks up a customer’s GPS coordinates to provide tailored resources and recommendations. You are new to the company and are considering culture in determining how best to manage the project. What can you examine to evaluate culture?
Select one
500.
You are the project manager for a large software development project. Your project is being performed under contract, and the project has just been canceled. Which of the following processes should document the level of completeness of the project?
Select one