New PMP Question & Answers with explanation
A seller began a project that was contracted on a time-and-materials (T&M) basis. Based on the agreed-upon rates and effort, the initial contract amount was $100,000 over a one-year period. However, when the project was completed, the total contract value turned out to be $350,000 over a two-year period. What mechanism could the buyer have used to prevent this unlimited cost growth and schedule change?
Select one
In a multi-phase project, the procurement team decided to close the procurements applicable to a particular phase of the project. What happens to unresolved claims?
Select one
During the procurement process, a contractual relationship is established between a buyer and a seller. During the contract lifecycle, what is the correct sequence in which the following terminology is applied to a seller: Vendor, selected source, and bidder?
Select one
Many organizations consider contract administration to be an administrative function separate from the project organization. Who carries out the function of contract administration in such organizations?
Select one
As part of the procurement process, the procuring organization elected to have an estimate of costs prepared by an outside professional estimator. The estimator came up with an estimate of $500,000. However, the cost estimates prepared by prospective sellers were in the range of $200,000. How can this be best interpreted?
Select one