237 New PMP Quality Questions & Answers with explanation

221.
Which of the following is not a part of the data gathering tools used in Control Quality process?
Select one
222.
Measuring the quality of items in a sample on a pass/fail basis is:
Select one
223.
Julia is managing a water treatment plant construction project. A new government has recently been sworn in. During the election campaign, the winning candidate made a number of commitments regarding environmental control reforms. Julia is not sure how the new government and its future policies might affect her project. This is an example of:
Select one
224.
As a project manager, you are responsible for determining and delivering the required levels of both grade and quality. Select which of the following statements you disagree with.
Select one
225.
The term ________ indicates the degree to which a particular product or service meets requirements, while _____________ indicates a category or rank used to distinguish that item from other similar items.
Select one
226.
What is the process of random selection and inspection of a work product?
Select one
227.
Which of the following processes are usually not performed continuously, but rather, performed periodically as needed:
Select one
228.
You have a contract to build a manufacturing plant in Kuala Lumpur. However, you are not familiar with the building codes in Kuala Lumpur or Malaysia, so you are reviewing all their building codes prior to “turning a shovelful of earth.” This is an example of:
Select one
229.
An automotive designer uses a certain technique to determine which combination of suspension and tires will produce the most desirable ride characteristics at a reasonable cost. To do this, the designer employs a statistical framework and systematically changes all the important parameters instead of changing the factors one at a time. This method is known as:
Select one
230.
Project managers need to be aware of Student Syndrome, also known as procrastination, which means that people start to apply themselves only at the last possible moment before the deadline. This concept is similar to Parkinson’s Law which states that:
Select one