41.
Which of the following reflect key values listed in the Agile Manifesto?
Select all right
42.
Which of the following influences the use of Agile approaches?
Select one
43.
A PMO leader is guiding the organization through Agile adoption. What characteristics should she consider when evaluating organizational readiness of Agile approaches?
Select three
44.
You work in an environment that uses a combination of delivery approaches, namely, Agile and Predictive approaches, with one-month release cycles. The vice president of your division has told you to report the status of the project budget for the current release as on track. You have experienced three budget overruns in the past six months and know that the status of the budget for the existing release is poor. However, you also know there is a repayment coming on one of the procurement work orders that will reverse almost all of the cost overruns you’ve experienced for this latest release. Which of the following do you know to be true regarding this question?
Select two
45.
A project manager is responsible for a project that consists of Agile team members dispersed across four time zones. The team has experienced communication issues as a result. What can the project manager do to alleviate the communication challenges?
Select two
46.
Which of the following best describes the role of a product owner within an Agile team?
Select one
47.
You are a lead project manager for a company that develops and manufactures healthcare devices. Your team has recently begun to adopt Agile practices after receiving the directive from the division president. What power type is at play in this scenario?
Select one
48.
A project manager working within an Agile PMO is using a new approved contractor to fast-track the implementation of cloud-based solutions for her project. As part of overseeing the procurement activities for the project, she conducts a structured review of the work performed by the contractor. Which tool and technique does this question describe?
Select one
49.
In flow-based Agile, what questions are teams likely to pose during stand-ups?
Select two
50.
One of the core tenants highlighted by Agile approaches is the value of flow versus focusing on how people are utilized. Which of the following reflect benefits of optimizing flow to attain value?
Select two