137 New PMP Questions & Answers with explanation

71.
Which of the following best describes how Planning activities are performed in a highly adaptive (Agile) life cycle?
Select one
72.
Predictive, iterative, incremental, and Agile are all types of what?
Select one
73.
Which of the following documents identifies 12 principles that are the focus of the Agile approach?
Select one
74.
An Agile-based team holds monthly status review meetings with the product owner to review deliverables produced post-iteration. Following the demo, the product owner uses part of the meeting to facilitate a general status review for the project. A good status review meeting uses which type of communication method?
Select one
75.
All of the following are Agile and Lean frameworks except for which one?
Select one
76.
Which of the following best describes an Agile life cycle?
Select one
77.
Agile project management can best be described as which of the following?
Select one
78.
Which of the following represents a benefit of using an Agile approach to manage projects?
Select one
79.
Kaylee has been managing projects for more than a decade and has largely used the waterfall method. She has recently taken a new job for a company that builds software for mobile devices and has begun studying the Agile method, which is largely used by this company. She begins by studying the Agile principles. What is the formalized document called that identifies 12 principles of the Agile approach?
Select one
80.

Match the following roles in the agile methodologies with their titles. 

Matching
Role Description
Product owner
The title similar to a project manager in the Lean methodology
Sensei
The title similar to a project manager in the Kanban methodology
Flow master
A Six Sigma title
Team facilitator
Also known as the Scrum master. Coordinates the work of the sprint
Black belt
The liaison between the Scrum master and the stakeholders in a Scrum methodology. Also known as the voice of the customer