New PMP Question & Answers with explanation
A cost management plan contains a description of:
Select one
A project manager is analyzing the project to find ways to decrease costs. It would be best the project manager looks at
Select one
Your manager is worried about the project schedule. There is a critical deliverable due to the federal government in two weeks. If you miss the deliverable, you could lose the entire contract. To help reduce the manager's stress, you show him the earned value calculations you just completed. They show your cost performance index (CPI) is 1.25, your actual cost (AC) is us $400 million, and your planned value (pv) is us $490 million. Should you manager be comfortable?
Select one
The six-month project has 300 work packages and a us $600,000 budget. Three months into the project, 150 work packages are complete and us $300,000 has been spent. Which of the following is correct?
Select one
Identified risks are:
Select one