2,934 New PMP Questions & Answers with explanation

1011.
Marysil recently accepted a new role as lead project manager within a well-established healthcare company. Over the past three months she has worked hard to introduce new concepts and styles into the environment. She has been met with some resistance by Rachel and Ron, two colleagues who prefer different styles of leadership. Ron is a high-energy and enthusiastic leader who prefers to lead through inspiration and strong conviction. What type of leadership style does Ron follow?
Select one
1012.
Which of the following describes an incremental life cycle?
Select three
1013.
You are a project manager working for a technology company that develops smart Bluetooth-enabled wearables for dogs. The product currently under development features a harness that gently vibrates when the dog gets beyond a specified range from the owner’s smartphone. You are developing the application that controls the harness using an incremental approach and have decided to create a prototype to gain feedback from your top five customers. The prototype will contain only a subset of features. What technique is being used by the team?
Select one
1014.
A project manager looking to improve their emotional intelligence should focus on what?
Select two
1015.
You work for Writer’s Block, a service that reviews and critiques manuscripts for aspiring writers. You were assigned to be the project manager for a new computer system that logs, tracks, and saves submitted manuscripts along with the editor’s notes. You hired and worked with a vendor who wrote the system from scratch to your specifications. You are reviewing a report regarding certain aspects of the project’s performance, and one of the measurements on the report calculates the difference between the budget at completion and the estimate at completion. Which of the following does this describe?
Select one
1016.
You are using Crystal Red to manage your project. At the start of the project, you negotiated with leadership to colocate the team together within a large team for the duration of the project. Your intent is to set up an environment where team members can overhear conversations as they occur within the room to politely eavesdrop and engage in conversations as needed. What is this communication method called?
Select one
1017.
You are managing a software development project with a team that is colocated. The project is managed through a set of iterations that begin with the creation of story cards. The focus of each iteration is to deliver business value, with programmers working together in pairs and as a group. Which of the following are true regarding this question?
Select two
1018.
You are a lead project manager for a company that develops and manufactures healthcare devices. Recently, your team went through major organizational changes, which required resource shifts within project teams. One of your projects experienced a 50 percent change in team member assignments. While the change posed challenges initially, the team has finally settled and are focused on the project. What phase of the team development model is your project team currently in?
Select one
1019.
As a result of a face-to-face meeting you recently had, you have resolved an issue and have come away with an update to the issue log, change requests, project management plan updates, and project documents updates, and you have submitted a change request. You know all of the following are true regarding this except which one?
Select one
1020.
Your project team is struggling to complete the latest set of features, which requires advanced knowledge of facial recognition technology. After considering various options, you decide to create a war room. What are you hoping to accomplish?
Select one