2,934 New PMP Questions & Answers with explanation

1651.
You are working with your team on estimating how much time each activity will take. One of the documents you are using contains information on categories of labor, material, and equipment required to complete your project. You are also interested to see skill levels of your labor, any certifications required, and grade levels of your supplies. Which of the following documents would you primarily refer to for this purpose?
Select one
1652.
You are employed by a software development company as a project manager. Your company has a policy that a change control board (CCB) reviews all of the change requests for every project in your organization, and the CCB follows all the recommended activities outlined in the PMBOK® Guide. You and your project team do not serve as members of the CCB. Based on this scenario, which of the following activities might be performed by members of the CCB?
Select one
1653.
A project manager is leading a process improvement project for a factory operation. Currently, the project manager and the team are performing the Monitor and Control Project Work process. Which of the following activities might the project manager and the team conduct during this process?
Select one
1654.
You are managing a project to develop a new robot for a mining rescue company. You are currently performing a monitoring and controlling project activity, and you have discovered that some of the project work has not been performed according to the plan. If these issues are not fixed before the next customer inspection, your project might be canceled. You have analyzed the situation, and the corrective action will only require a minor adjustment to a configuration element. What should you do first?
Select one
1655.

You have just taken over a project to overhaul the company's telecommunications network. During your first week, you determine that the engineers spend at least 80% of their time responding to unexpected requests for information from different project stakeholders. Because of these interruptions, your engineers cannot focus on their assigned project activities, which is resulting in frequent network outages. What should you do first?

Select one
1656.

Recently, you promoted your star programmer, Sam, to lead the development team. Sam was a fantastic software coder, and you thought the promotion would mean that he could now share his expertise with the other development team members. However, you are surprised to learn that the performance of Sam in his new role is not meeting your expectations. Which empirical rule did you forget while considering the promotion of Sam?

Select one
1657.

You are a project manager planning a project to develop a new payroll system, and you are currently in the process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives. A project stakeholder has suggested that it would be helpful to have a visual depiction showing how people and other systems will interact with the new payroll system. You like the idea and want to address it. What is the best way to implement the stakeholder’s suggestion?

Select one
1658.

You are managing a project in Alaska to extend an existing oil pipeline, and you are about to start project planning. Due to the large size of the project along with the regulatory and environmental considerations, the development of a detailed project management plan will be critical. As a starting point for initial project planning, what is the first thing you should do?

Select one
1659.

You are facing problems decomposing the testing work package into the final activities required to complete the work package. Detailed testing plans and activities cannot be determined until the system is at least 50% developed and more details become available. The system development work package will take at least three months to complete. What is the best way to resolve this problem?

Select one
1660.

A project manager is leading the construction of a new office building. The project sponsor asks the project manager to email him a project document that was presented during the last project status meeting. The project sponsor states that he has forgotten the name of the document, but he remembers it contained the description, owner, source, priority, and status of product requirements. Which project document is the project sponsor requesting?

Select one