2,934 New PMP Questions & Answers with explanation

1671.

For the project with original project budget $1000 and both the Cost Performance Index (CPI) and Schedule Performance Index (SPI) equal 1. Assuming the project will continue to spend money at the same rate, what is the Estimate At Completion (EAC) of the project?

Select one
1672.

A project with Earned Value (EV) = $250, Actual Cost (AC) = $200 and Planned Value (PV) = $350. What is the Cost Performance Index (CPI)?

Select one
1673.

A project with Earned Value (EV) = $250, Actual Cost (AC) = $200 and Planned Value (PV) = $350. What is the Schedule Performance Index (SPI)?

Select one
1674.

A project with Earned Value (EV) = $1000, Actual Cost (AC) = $800 and Planned Value (PV) = $800. What is the Cost Variance (CV)?

Select one
1675.

A project with Earned Value (EV) = $1000, Actual Cost (AC) = $800 and Planned Value (PV) = $800. What is the Schedule Variance (SV)?

Select one
1676.

According to EVM, which term below represents the budgeted cost of the work to be completed to date?

Select one
1677.

According to EVM, which term below represents the outstanding amount of money required to finish the project?

Select one
1678.

A project with both Schedule Performance Index (SPI) and Cost Performance Index (CPI) of 0.80. The project is currently:

Select one
1679.

If a project has a Schedule Performance Index (SPI) of 0.90, this means that:

Select one
1680.
Which of the following helps a project manager determine possible causes of potential problems and actual problems?
Select one