1711.
If a data point falls outside the upper control limit of a control chart the process is said to be:
Select one
1712.
A team is using a fishbone diagram to help determine what quality standards will be used on the project. What part of the quality management process are they in?
Select one
1713.
When a product or service completely meets a customer’s requirements:
Select one
1714.
A project manager is working with quality professionals in the perform quality assurance process of the project. Which of the following activities is being performed?
Select one
1715.
At the end of a project, a project manager determines that the project has added four areas of functionality and three areas of performance. The customer has expressed satisfaction with the project. What does this mean in terms of success of the project?
Select one
1716.
All of the following are inputs to quality planning except?
Select one
1717.
Who of the following has primary responsibility for establishing design and test specifications?
Select one
1718.
Design of experiments:
Select one
1719.
Work on a project is ongoing when the project manager overhears two workers arguing over what a set of instructions mean. The project manager investigates and discovers that the instructions for the construction of the concrete footings currently being poured were poorly translated between the different languages in use on the project. Which of the following is the best thing for the project manager to do first?
Select one
1720.
The widget production project ¡s well underway. The requirements are clear that each widget must weigh between 0.320 and 0.325 ounces. The first day of test production resulted in 1247 widgets. Of the widgets inspected, 47 percent fell within the acceptable weight range. This is an example of?
Select one