New PMP Question & Answers with explanation
How can changes be made to a project management plan once the project manager baselines it?
Select one
Due to a tight project schedule, a project manager did not document lessons learned throughout the project cycle. However, at the end of the project, he finally documented the lessons learned. Your comment on this is:
Select one
One of the stakeholders of a project initiated a change request, which was then documented in the change control system. Who would typically be responsible for approving or rejecting the change request?
Select one
The sponsor of a project created a document that included the business need and the cost-benefit analysis. What would this document be termed as?
Select one
The list of identified risks is found in the risk register. However, the overall high-level project risks is first listed in the:
Select one