2,934 New PMP Questions & Answers with explanation

2751.
Project stakeholders are individuals and organizations who are actively involved in the project or who have an interest in it. Which of the following is not an internal stakeholder?
Select one
2752.
Caitlin’s project is behind schedule. She is planning to crash the project by allowing overtime to the project team. This approach can bring additional risks to the project. Which of the following is not a valid risk in this scenario:
Select one
2753.
Sandra is managing a complex ERP design and implementation project. The project team has recently been hired. It is an enterprise-wide project affecting many stakeholders. It is very important for each team member to properly understand and follow the project communication requirements in order to keep the stakeholders engaged and informed. Which of the following tools and techniques can Sandra use to ensure that team members properly understand the project’s communications requirements?
Select one
2754.
You are managing a construction project. Your company does not specialize in construction design so you outsourced the construction design to a third party. You are conducting regular procurement performance reviews and are dissatisfied. You want to carry out a detailed audit of the design supplier’s work processes to determine the root cause. Can you do that?
Select one
2755.
Mary is currently drafting a stakeholder engagement plan for her new website development project. Her organization has strict communication guidelines. Mary wants to ensure that her stakeholder engagement strategy aligns with the organizational communications guidelines. Where can she find these guidelines?
Select one
2756.
As an experienced PMP, you have found that running a WBS meeting is tricky because you need to find a balance between insufficient decomposition and excessive decomposition. When items are excessively decomposed, it leads to all the following except:
Select one
2757.
Which of the following can NOT be used to measure business value?
Select one
2758.
Ben is the project manager for a mobile application development project. Due to a recent technological development, a significant change in the product design is required. This change would require a 25 percent increase in the project budget. Ben prepares a detailed report and emails it to the project sponsor, and the sponsor acknowledges the receipt of the report. What should Ben do next?
Select one
2759.
You are the project manager responsible for building a 100,000-squarefoot data center. One of the scheduled activities in your plan is to install the Computer Room Air Conditioning (CRAC) units. However, before beginning the installation of the units, a raised floor must be installed for the units to bolt to. This is an example of what type of dependency?
Select one
2760.
Robert wants to assign a risk owner for every project risk for which a risk response action is planned. Where must he update this information?
Select one