767 New PMP Process Questions & Answers with explanation

121.
Due to time constraints, a project manager omits the review of previous lessons learned. What is a potential impact of this decision?
Select one
122.
A project has ended; however the project manager and project team members are still called to solve technical issues, make some small changes, and evaluate new requirements. What should the project manager do to guarantee the product or service developed by the project now has operational support?
Select one
123.
Without considering all the implications, a project sponsor requires that the project team be composed of resources located in three locations in three different time zones. This is expected to save costs and provide the optimal project team. Where should this be reflected in the project charter?
Select one
124.
The project manager observes that team members are accepting a number of changes to the deliverables with little attention to ensuring acceptable standards. When questioned, the team members reply that the changes are relatively minor. What part of the project management plan should the project manager review with the team?
Select one
125.
A project manager is working on a new project to address gaps in a previously completed project. What should the project manager do first?
Select one
126.
A project is initiated based on the approved scope. During implementation of the project design, a team member states that the product will not meet the requirements in a particular scenario. Fixing the issue will increase the scope and costs, and the project will miss the deadline. The project sponsors do not have additional funding to support the project. What should the project manager do?
Select one
127.
During the planning phase of a project, the project manager learns that the financial director, a key stakeholder, will be unavailable for three weeks. What should the project manager do first?
Select one
128.
A project needs resource support from a supplier because several team members have been transferred to another project. Concerns arise about the cost risk of using a supplier at this stage of the project. The project manager is working with the procurement team to establish specifications and the type of contract that should be used. What type of contract should the project manager recommend?
Select one
129.
During a project's execution phase, 100 products were developed based on the originally approved blueprint. The project team randomly selects 20 products to evaluate against the quality plan. What is the project team performing?
Select one
130.
A project manager is preparing the monthly project status report. Some new risks have been identified that could impact important key milestones. What should the project manager reference before presenting this new risk information?
Select one