Free 2,500+ PMP questions for practice

To practice your pre-exam and review each question with detail explanation, let try with our FREE Exam tool

New matching, multiple choices exam questions from domain, process, business environment and agile which align with the new 2021 exam contain outline

142 New PMP Process Questions & Answers with explanation

91.
You are a project manager for Community Trends, a nonprofit organization. Your project has come about because of a social need. You’re calculating performance measurements and using actual costs to date, and you assume that ETC work will be completed at the budgeted rate. You know the following information: BAC = 900, ETC = 65, PV = 500, EV = 475, and AC = 425. Which of the following is the correct expected total cost at completion, given this situation?
Select one
92.
A project has the highest probability of completing successfully at which stage of the project?
Select one
93.
Direct and Manage Project Work, Manage Quality, and Conduct Procurements are processes belonging to what project management process group?
Select one
94.
Which of the following best describes the purpose of carrying out activities associated with planning stakeholder engagement?
Select one
95.
A project manager is performing activities associated with the Plan Procurement Management process. He is attempting to determine, along with the relevant subjectmatter experts, whether it makes more sense to develop internally or purchase a deliverable. What tools or methods can he use to produce a successful outcome?
Select one
96.
You use a predictive approach to managing projects and have just completed your cost baseline. Next, you begin working on determining funding requirements. Which of the following is true?
Select one
97.
Which of the following best describes overall project risk?
Select one
98.
Alyssa is a project manager tasked with managing an infrastructure project that will consolidate five data centers into one. She is currently facilitating the estimating process to calculate the duration of the project’s activities. Alyssa knows that she has reliable information and is therefore planning on using an estimating technique that will yield a highly accurate estimate with minimal effort expended. What estimating technique is she planning on using?
Select one
99.
Roshoud is the VP of customer operations for Galactic Kidz and project sponsor of the latest project, called Project G. He sits down with Sally, the project manager, to discuss the current budget estimate. Roshoud expresses his concerns to Sally over the budget being far greater than originally anticipated and asks her to course-correct. What produces the greatest expense on most projects?
Select one
100.
You are working on the communications management plan for your project and have considered the timing and need for updated information by you and your four stakeholders. Your organization has modern, up-to-date technology that your stakeholders and staff have used before, so you anticipate that supplying the information and updates to your stakeholders and team members will be a breeze. Which of the following is true?
Select one