769 New PMP Process Questions & Answers with explanation

81.
A multinational company initiates a project to develop a human resource information system (HRIS) to centrally manage human resource and payroll processes. So far, the project manager has considered the regulatory framework of the project and reviewed historical data on the company's human resource practices. The project manager is worried about project risks. What should the project manager do?
Select one
82.
A risk is identified during a project that was not anticipated during planning. How should the project manager respond to the risk?
Select one
83.
While developing the project schedule, the project manager realizes that the high-level timeline is unrealistic due to longer-than-expected procurement lead times for certain key project components. What project document should the project manager update?
Select one
84.
A project issue is identified after implementation in the production environment. What tool or technique should the project manager use to identify the reason for the issue?
Select one
85.
For a long-term infrastructure project, the project manager must acquire suppliers with the lowest possible risk due to the global business climate. What type of contract should the project manager use?
Select one
86.
A project manager is ready to close a project. What should the project manager do next?
Select one
87.
During project implementation, the marketing department informs the project manager that the product's market requirements have changed. These changes were not anticipated, may significantly influence potential sales numbers, and could impact project scope. What should the project manager do?
Select one
88.
A project manager receives the preliminary scope, assumptions, and restrictions for a new project. What should the project manager do first?
Select one
89.
A project is 45 percent complete when a project manager learns that an outsourced key resource will be unavailable for an extended period of time. This will have a serious impact on the project's schedule and budget. What should the project manager do?
Select one
90.
During a periodic review with stakeholders, the project sponsor asks the project manager how deliverables will be verified for accuracy and accepted. Where can the project manager find this information?
Select one