New PMP Question & Answers with explanation
An experienced project manager was assigned a project of small scope. Which of the following could be true of the project?
Select one
Mark is managing a telecom network deployment project. The buyer of the telecom network is an external entity. Recently, the customer requested that all future project updates be posted to their information system automatically. In order to implement this, the project team needs to customize their project management information system so it can be integrated with the customer’s information system. This is a new customer requirement that was not a part of the original project’s scope. What should the project manager do?
Select one
You were just hired by a waste management company to develop a solid waste management program in an underdeveloped country. The project will be on a build-operate-transfer basis and will have a two-year duration. At the close of the project, local authorities will run the program. The World Bank sponsors the project, and a large consortium has received the award. Your company is subcontracted to do this project along with two more contractor companies. After the project scope was finalized, you developed a cost estimate of US$5.5 million. The sponsor reviews your detailed costing sheets and is concerned about the total cost figure. He tells you that the maximum allowable budget he can allocate for this project is US$5 million. What should you do?
Select one
Which of the following approaches deliberately spends less time trying to define and lock project scope early during the project and spends more time establishing the process for requirements gathering, scope definition and refinement?
Select one
In projects with adaptive life cycles, the overall scope of the project will be decomposed into a set of requirements and work to be performed, sometime referred to as:
Select one