New PMP Question & Answers with explanation
You are managing a project that has a task to translate several pages of a document into Spanish. This is similar to a project done last year when a document was translated into German. You are not sure how long it will take to translate into Spanish, so you look at the project plan from the German translation and use that activity duration for your current project. What type of estimating is this an example of?
Select one
While developing your project schedule, you have asked everyone to provide a list of planned vacations over the next three months, and you have applied this information to the tasks that each person is responsible for. What also needs updating?
Select one
You are running one week behind on a project due to a late delivery by a vendor. You are forced to compress your project schedule due to a government-mandated end date that constrains your project. After meeting with your team, the decision is to work several tasks in parallel that were scheduled to be run consecutively. This is an example of:
Select one
A technique that calculates multiple project durations with different sets of activity assumptions and variables is:
Select one
There are two activities on your schedule: 1) Install server in lab, and 2) Move server into the data center. However, the second task cannot start until the server has run in the lab for five days without failure. This is an example of what?
Select one