The cost estimates for a project are in the range of +/- 5 %. What phase is the project likely to be in?
Select one
Bottom-up Cost estimating is typically motivated by the size and complexity of:
Select one
Breaking down project activities into smaller components in order to obtain a more accurate cost estimate and then aggregating the estimates of the lower-level components is:
Select one
Costs incurred in one area of a project can offset costs in another area of the same project. However, it is not enough to consider only the costs of project execution when making project decisions. What other costs external to the project must also be considered?
Select one
Megawatt is estimating the expected cost of a new ERP system deployment project using the actual costs of an earlier similar ERP system deployment project as the basis for the cost. This is what type of estimating?