New PMP Question & Answers with explanation

As the project manager of a large project, you have just completed the Estimate Costs process. As you begin the Determine Budget process, which of the following would you require as inputs to the process from the Estimate Costs process?
Select one
A project manager presented earned value analysis data in a tabular format in a performance report. Another way the project manager could have presented the earned value analysis data is with:
Select one
The most recent analysis of Microcorp's new fabrication facility renovation project shows a CPI value of less than 1.0. What does this indicate?
Select one
Which of the following indicates the required cost performance in order to complete the project on budget?
Select one
The formula for Cost Variance is:
Select one