2,934 New PMP Questions & Answers with explanation

1091.
Calculate the to-complete performance index (TCPI) based on the current EAC, using the following values: BAC = 15,000, AC = 12,000, EV = 10,000, EAC = 17,000.
Select one
1092.
A project manager became aware of a disagreement between two developers who have been paired together to write code. Which conflict-resolution technique should the project manager use to create a win-win situation?
Select one
1093.
According to Edward de Bono, what type of alternatives analysis can be used to determine a project’s scope?
Select one
1094.
Your organization is experiencing a shake-up at the top levels of management. Your project team has expressed concerns that their project might be canceled because of the changes going on at the top. Sure enough, your project team was correct in their suspicions. You’ve received notice that the project is canceled. The team has one remaining deliverable for the project that was scheduled for completion next month. Your next step is to document the work results to date. Which of the following describes the tools and techniques of the process this question describes?
Select one
1095.
The president of the company has asked you to lead a large new project that links to the company’s number-one strategic priority. As a result, you will need to transition one of your other projects to another project manager. During a transitionary meeting, your colleague asks to see what training has been planned for the team. Where is this information captured?
Select one
1096.
You are the project manager for Changing Tides video games. Your project is a longterm project and will be completed in three phases over the next two years. You have gathered the inputs for the Estimate Activity Durations process and are ready to produce the activity duration estimates. Your sponsor would like a project estimate for all three phases by the end of the week. He understands that at this stage it will be a rough order of magnitude estimate and not entirely accurate. Which of the following tools and techniques will you use to produce this estimate?
Select one
1097.
A project manager is in the process of building the project team and obtaining the materials and supplies the team will need to achieve the project’s planned outcomes. In what activity are they engaged?
Select one
1098.
Which of the following are components of the sender/receiver communication model?
Select three
1099.
You are in the process of translating the quality management plan into executable quality activities that account for existing quality policies. What process are you in?
Select one
1100.
Marysil, an enterprise project manager for Cups on Fire, kicked off activities to develop the schedule. To date, she has generated the schedule management plan and led the team through a decomposition of work packages into activities. Now, she and the team are sequencing activities. She plans on displaying a visual using a network diagram during the next meeting. What network diagramming method is she most likely to use?
Select one