2831.
A first-time project manager wanted to have a “perfect project.” This manager informed the customer that this project would not accept change requests of any kind and that the scope would need to be defined precisely at the very start of the project. The customer agreed to this request. What would your comment on this situation be?
Select one
2832.
A project manager has scheduled technical training for his or her project team members to increase their skills. During which of the following processes will the team member receive this training?
Select one
2833.
Your project calls for communication with an extremely large audience. What communication method would be appropriate under such circumstances?
Select one
2834.
If you are writing a proposal for additional funding, which communication style should you choose?
Select one
2835.
Which of the following two project documents are sometimes perceived as containing a certain degree of redundancy?
Select one
2836.
You have completed your estimates for your project and have determined that it will take 10 months to complete. However, your project sponsor insists that it be completed in nine months. How do you handle this?
Select one
2837.
A project manager prepared a composite resource calendar. Which of the following is unlikely to be part of the resource calendar?
Select one
2838.
You have just become the project manager of a project already in execution. During your first week on the job, you receive multiple requests from different stakeholders asking for project reports in various formats. These requests overwhelm you. What should you do first?
Select one
2839.
A project was awarded based on a competitive proposal. Management made a commitment that a few key team members would work on the project. When such assignments happen, they are:
Select one
2840.
During a cost performance review with certain senior officers from the finance department, you discover there are certain inconsistencies in the way cost performance reporting is done, and you obtain data that shows these officers are deliberately misleading senior management. What should you do?
Select one