2,934 New PMP Questions & Answers with explanation

281.
A project manager needs to outsource 1,200 resource hours. Due to internal policies, each provider must understand the requirements. What should the project manager do to ensure this?
Select one
282.
During project execution, a functional manager identifies a new internal risk about the outsourcing team. The functional manager asks the project manager for a fast solution that will not negatively impact the project. What should the project manager do?
Select one
283.
A senior manager wants to use an essential project resource for another project. What should the project manager do?
Select one
284.
A marketing team identifies the target audience for their new website. They want to know the preferred tastes of this target audience. What tool or technique should the project manager use?
Select one
285.
A project manager is working with stakeholders to identify strategic and operational assumptions and constraints. However, not all stakeholders are consistently providing input. What should the project manager use to enhance stakeholder input?
Select one
286.
An experienced project manager resigns, and a new project manager joins the team. During the initial assessment of project documentation, the new project manager discovers that the risk register has not been updated for the past month. What should the project manager do first?
Select one
287.
A project's workload is high and resources are overloaded. When management decides to outsource some services to keep the project on schedule, what document should the project manager revise?
Select one
288.
A project to migrate an organization's email system to another platform creates an unexpected, but significant, issue on another business-critical system. What should the project manager do?
Select one
289.
A project manager is reviewing approved change requests made within the past month. The process has been efficient, but implementation is taking longer than originally planned. What should the project manager do?
Select one
290.
A project is in its execution phase. Due to a new regulation, the client asks for additional documentation to be delivered within the contract. What should the project manager do?
Select one