767 New PMP Process Questions & Answers with explanation

381.
Which of the following best describes procurement audits?
Select one
382.
The project manager of a multiphased gaming project made a phone call to one of her virtual project team members abroad regarding an upcoming schedule activity that the team member was responsible for. The project manager notified the team member that due to an unplanned risk, a prototype would be built into the schedule, and it was important that her activity be completed according to the plan. The project manager noticed that the team member did not say much during the call, and she hoped that the team member understood. What did the project manager fail to do?
Select one
383.
A project manager sits down with the project sponsor to review progress. The sponsor asks to see the short-term and long-term timeline for realizing benefits. What document can the project manager reference that contains this information?
Select one
384.
Which of the following best defines target benefits?
Select one
385.
Upon returning from lunch, you discover that a quality audit will be taking place. Some of the team members are upset, since there is an approaching deadline, and have therefore requested that the audit be moved to the following day. As the project manager, what should you do?
Select one
386.
A project manager is currently working on a pharmaceutical project. The activities that will produce the deliverables of Phase 1 are currently being planned out in detail. All other work will be planned out at higher levels until additional product details are known through testing results. This strategy is known as:
Select one
387.
You are currently assigned to work on a project involving the release of a new pharmaceutical drug. The vice president (VP) of strategic partnerships, who to date has not been a part of the project, asked to see the work performance data. This raises a red flag for the following reason:
Select one
388.
The project manager had received two complaints that three project team members were arguing over the interpretation of schedule analysis results conducted the previous day. The project manager had waited to see whether they would work it out among themselves, but another two complaints were made that the situation was affecting the work of others. What should the project manager do?
Select one
389.
If activity A has a duration of 10 days and activity B has a duration of 7 days with a 2- day lag, what is the overall duration of both activities combined, given a start-to-start relationship with an assumption that both activities will begin as soon as possible?
Select one
390.
You are a project manager working as a consultant for a company that is in startup mode. One of your responsibilities for this week is to create an organizational chart. What format can you use to display an organizational chart?
Select three