New PMP Question & Answers with explanation
You have a schedule activity that can be delayed without delaying the early start date of any subsequent activities. This is an example of:
Select one
Jack is the project manager of a project that is halfway through its execution. He is currently looking at the work schedule. He adjusts a few of the schedule milestones and imposes date constraints for some of the work packages. This relates to which of the following processes?
Select one
Mandatory dependencies are those that are inherent in the nature of the work being done. They often involve physical limitations, such as on a construction project when it is impossible to erect the superstructure until the foundation is built. According to the PMBOK, a mandatory dependency is also:
Select one
A manager asked to see a list of milestones in the project. This would be available as an output from the:
Select one
A construction project requires that government environmental hearings be held prior to site preparation. What kind of dependency is this?
Select one