New PMP Question & Answers with explanation
Which of the following may help in ensuring that certain bidders in the procurement process do not receive preferential treatment and that all prospective sellers have a clear and common understanding of the procurement?
Select one
The termination clause and alternative dispute resolution (ADR) mechanism for each procurement in a project is in the:
Select one
The State of New York has contracted with your company to provide a claims payment system for Medicaid benefits. In the contract, a clause states that the State of New York can review your work processes and deliverables. This is an example of:
Select one
Crashing is an effective schedule compression technique at times when a project is struggling behind schedule. However, increasing the number of resources to twice the original number of the resources does not always cut the time by half. This is due to:
Select one
Andy’s project stakeholders are not happy as the project is lagging behind schedule. During the executive committee meeting, Andy requests all stakeholders to keep their calm as most of the project deliverables have been completed and only quality inspections of these deliverables is pending. He assures the stakeholders that he is planning to crash the project to meet the completion deadline. What should be the stakeholders’ biggest concern now?