New PMP Question & Answers with explanation

A project with Earned Value (EV) = $250, Actual Cost (AC) = $200 and Planned Value (PV) = $350. What is the Schedule Performance Index (SPI)?

Select one

A project with Earned Value (EV) = $1000, Actual Cost (AC) = $800 and Planned Value (PV) = $800. What is the Cost Variance (CV)?

Select one

A project with Earned Value (EV) = $1000, Actual Cost (AC) = $800 and Planned Value (PV) = $800. What is the Schedule Variance (SV)?

Select one

According to EVM, which term below represents the budgeted cost of the work to be completed to date?

Select one

According to EVM, which term below represents the outstanding amount of money required to finish the project?

Select one