New PMP Question & Answers with explanation
A project with Earned Value (EV) = $1000, Actual Cost (AC) = $800 and Planned Value (PV) = $800. What is the Cost Variance (CV)?
A project with Earned Value (EV) = $1000, Actual Cost (AC) = $800 and Planned Value (PV) = $800. What is the Schedule Variance (SV)?
According to EVM, which term below represents the budgeted cost of the work to be completed to date?
According to EVM, which term below represents the outstanding amount of money required to finish the project?
With reference to the diagram below, it can be inferred that the project is currently: